W aktualnościach znajdziesz również:
Renovations at school
15 September 2014
There were some renovations made at school in Szczeglino during summer holidays. The cost was estimated at around 11.000 PLN . The renovations included: the overhaul of the school’s long corridor which now has a more aesthetic look, the substitution of damaged carpets with floor tiles, the mounting of suspended ceiling, the refreshing of old door and walls.
“Refugium” assosiation, which is running the school, also had its part in preparing the school for the new school year. Class I was painted, stairs leading to the first floor were renovated with fire-resistant plates to protect them, and the installation of an additional handrail contributed to the safety of younger students moving up the stairs. As a result of the renovation of the stairs, it was possible to set up a new changing room. The existing changing room was also refreshed.
We greeted the new school year with joy, seeing how the building has changed.